A camp plant that trips is undersized and one that burns fuel is
oversized, and the argument usually comes down to a single number: diversity.
Add up every nameplate in every cabin and you have the connected load; what
actually runs together is the peak demand. Design peak equals connected load
times the diversity factor.
The difficulty is
what factor to use. The 60–70 percent common in housing is often too low on a
camp. Campsite data makes the point: the old practice took 0.65 for twenty
pitches and 0.4 above fifty, on the reasoning that not everyone boils water at
once. But modern motorhomes carry roof air conditioning, induction hobs and
200–800 Ah lithium banks, with pitch supplies rising from 6–8 A to 16–25 A. Add
hot days when everyone cools at the same time, and gas-free cooking that puts
every induction hob on together, and the old factors fail. Current guidance is
1.0 up to about twenty pitches, and no lower than 0.8 beyond that.
Camps have one more
concentrator: shift change. At seven in the morning and seven in the evening
everyone showers, cools, boils and charges at once, and that half hour runs far
above the daily average. So peak sizing cannot look at installed equipment
alone; it has to ask when things coincide. Take six cabins at 1.5 kW of
cooling, 2 kW of water heating and 0.5 kW of everything else: 24 kW connected.
A 0.6 factor gives 14.4 kW, the plant gets ordered to that figure, the real
shift-change peak reaches 24 kW, and the result is an overload. The missing 10
kW is one outage.
Name: Mr. Zhang
Mobile:8613222235952
Tel:8613167199094
Whatsapp:8617315222516,8613167199094
Email:skyzhang@podprefab.com
Add:Room B1701, Building 4, Dongfang Xintiandi, Yangshe Town, Zhangjiagang, Suzhou City, Jiangsu Province, China