This case is based on a highway project in Guangzhou. Pile driving for highway pavement is an outdoor mobile construction scenario with no stable municipal power grid on site. The conventional power supply solution relies purely on diesel generators. This project adopts a diesel-storage hybrid smart power station (diesel generator + energy storage hybrid) to replace the traditional pure diesel power generation, delivering continuous power for pavement pile driving equipment.
Power Station Configuration: 2 sets of 360kW diesel generators + 2 sets of energy storage systems
Average load power: 552.5kW
Daily operating hours: 12h, daily power consumption: 6,630 kWh
Monthly working days: 28 days, monthly power consumption: 185,600 kWh
Construction period: 12 months, total power consumption: 2,227,700 kWh
|
Items |
Conventional Pure Diesel Generation |
Diesel-Storage Hybrid Smart Power Station |
|
Power generation per liter of diesel |
1.7 kWh/L |
2.5 kWh/L |
|
Total diesel requirement |
1.3104 million L |
0.8911 million L |
|
Diesel price |
7 RMB/L |
7 RMB/L |
|
Total diesel cost |
9.1728 million RMB |
6.2377 million RMB |
Cost Savings: With the same power consumption, the smart power station saves 1.678 million RMB in fuel cost compared with conventional diesel generation.
This diesel-storage hybrid solution can be applied to highway subgrade piling, bridge foundation piling, slope support piling and other field infrastructure construction sites. It replaces conventional pure diesel generators to achieve cost reduction and efficiency improvement.
Name: Mr. Zhang
Mobile:8613222235952
Tel:8613167199094
Whatsapp:8617315222516,8613167199094
Email:skyzhang@podprefab.com
Add:Room B1701, Building 4, Dongfang Xintiandi, Yangshe Town, Zhangjiagang, Suzhou City, Jiangsu Province, China